Legal Question in Business Law in California
What is the length of time to enforce a mechanics lein?
What is the length of time in the state of Califonia to file claim on a mechanics lein?
2 Answers from Attorneys
Re: What is the length of time to enforce a mechanics lein?
With some exceptions you have 90 days to file suit to foreclose upon a mechanic's lien.
If you would like a free initial consultation, please call me at (818) 991-6664. I have over twenty-five years experience.
Good luck and thank you for your inquiry.
Re: What is the length of time to enforce a mechanics lein?
This question belongs under the heading of construction law, and if you re-ask it under that LawGuru topic heading you should get more and better replies.
As a genralist in business and real estate law, I can tell you where to look.
Take a look at Civil Code section 3144. It says (with some exceptions) that a mechanic's lien expires after 90 days from recording a claim of lien (not the be confused with the preliminary notice!) unless an action to foreclose the lien is commenced in a proper court.
Related Questions & Answers
-
Who is ''color-blind''? I just recently had my car painted. I looked thru the body... Asked 6/11/05, 10:10 am in United States California Business Law