20 day notice

what notice would you file after you have filed a

20 day notice?


Asked on 11/11/02, 10:35 am

1 Answer from Attorneys

Gary Redenbacher Redenbacher & Brown, LLP

Re: 20 day notice

I assume you're talking about a preliminary or prelien notice. I'm not sure what you're referring to when you say "what notice would you file after you have filed a 20 day notice."

Are you asking what the next step is if someone hasn't paid you? If so, the next step is to record a mechanic's lien. Remember, though, that a mechanic's lien is just one of several remedies available to contractors.

Read more
Answered on 11/12/02, 1:01 pm