We have been told that a mechanic's lien, which has been filed, is only good for 90 days. What can a contractor do to further secure the thousands of dollars he is still owed by an LLC group who has not sold the home, nor payed for septic and foundation, as well as the garage


Asked on 2/11/08, 8:41 pm

1 Answer from Attorneys

Carl Starrett Law Offices of Carl H. Starrett II

Re: Lien for owner's non payment of work done

You need to file a lien foreclore/breach of contract lawsuit in order to enforce the lien and/or get a money judgment. Without doing so, a lien is of little value.