Legal Question in Construction Law in California
Lien
Is it true that a contractor who has put a lien on a property, has 90 days to file an action, otherwise the lien expires? There is no written contract.
Asked on 4/02/05, 10:48 pm
1 Answer from Attorneys
Philip Iadevaia
Law Offices of Philip A. Iadevaia
Re: Lien
A mechanic's lien must be foreclosed on within 90 days. After 90 days, the lien is null & void. But you still have to sue to have it removed from the property.
Answered on 4/04/05, 11:30 am