Is it true that a contractor who has put a lien on a property, has 90 days to file an action, otherwise the lien expires? There is no written contract.


Asked on 4/02/05, 10:48 pm

1 Answer from Attorneys

Philip Iadevaia Law Offices of Philip A. Iadevaia

Re: Lien

A mechanic's lien must be foreclosed on within 90 days. After 90 days, the lien is null & void. But you still have to sue to have it removed from the property.