Legal Question in Construction Law in California
Is a mechanic's lien needed/desirable when contractor finances for client?
We are a landscape contractor in California. A client has cash to pay for 2/3 of the contract cost and wants us to accept 11 monthly payments for the balance of contract cost. They're willing to sign a promissory note, with interest. Should we file a mechanic's lien to protect our interests? If so, when should we file -- upon completion of 2/3 of the job, upon final completion of the job, when client misses a payment? Thank you for your help.
2 Answers from Attorneys
Re: Is a mechanic's lien needed/desirable when contractor finances for client?
Either would be a terribly improper use of the mechanics lien remedy.
A mechanics lien may only be recorded when labor and/or materials have been provided to the property, not before; and it certainly cannot be used as a securitization vehicle.
Moreover, the lien itself is only good for 90 days, during which time foreclosure proceedings must be instituted. Otherwise, the lien goes stale, and you must remove it.
From a practical standpoint, don't finance your clients unless you can afford it. You are better off getting the money in full. Your client can finance the job using someone else's money, not yours.
Good luck.
***No Legal Services or Attorney Client Relationship - Although this email may provide information concerning potential legal issues, it is not a substitute for legal advice from qualified counsel. You should not and are not authorized to rely on this email as a source of legal advice. Until a formal Retainer Agreement is executed, any communication between you and The Guerrini Law Firm cannot create any attorney-client relationship between you and The Guerrini Law Firm.***
Re: Is a mechanic's lien needed/desirable when contractor finances for client?
A mechanic's lien will not help you and it will also expire after 90 days unless you file a lien foreclosure lawsuit. Your customer really should finance their project elsewhere.
If you still want to take on this project and still provide financing, you should at least have the promissory note secured by a deed of trust. Contact a local attorney for further assistance.
Related Questions & Answers
-
Preliminary 20-day notice i was an owner/builder of a swimming pool. my wife and i... Asked 12/04/06, 11:01 pm in United States California Construction Law
-
Mechanics Lien What does it mean to me if a subcontractor files a mechanics lien... Asked 11/26/06, 12:21 pm in United States California Construction Law