Does a Mechanic's Lien have to be recorded before a Stop Notice is sent?
Asked on 12/17/10, 9:29 am
1 Answer from Attorneys
No. They are parallel or alternative remedies for non-payment. If you do not have a direct contact with the owner, however, you must have given the 20-day notice before or within 20 days after you started work on the project, or you have no rights to either one.
Answered on 12/22/10, 10:43 am
Related Questions & Answers
-
Can a private organization (rotary, moose lodge) request a member to get anger... Asked 12/16/10, 8:15 am in United States California Construction Law
-
I hope you can help. I had some construction work done and hired an unlicensed... Asked 12/13/10, 1:21 pm in United States California Construction Law
-
When i was married, we had a construction business. there is a personal judgment... Asked 12/01/10, 12:27 pm in United States California Construction Law
-
I entered into a bare-bones contract with an Architect. when we began working... Asked 11/21/10, 6:42 pm in United States California Construction Law