Legal Question in Construction Law in California

First original contract is passed the deadline

so a

new agreement made via e-mail which is now also passed deadline.

because contractor close to finishing with home remodeling, Owner and Contractor verbally agree to continue and finish the remodeling with no new due date mention.

One day before the project was to be now fully completed Owner decides to change door locks(I had the keys to the previous locks) and picks up a day laborer from home depot to finish the remaining work(about a full days work).

Owner Says I had done damages to which he now has to pay someone else to fix and will be deducted from my total price. and All my work was done bad to which he inspected and approve off throughout the project.

* Contract unequal was more in favor/protecting him and with more consequences obligations to me

* the owner(realtor/developer) wrote the contract and said to just signed it seems a lot of work but there�s parts in the contract that doesn�t pertain to me or my duties and he will rewrite it later which he never did) because he was running late pressure me to sign it.

* 1st2ndcontract passed deadline because materials missing and little time for scale of the project.

I was paid $0

2011 Started on may 26 -ended(changing locks) july 15


Asked on 10/05/11, 4:30 am

1 Answer from Attorneys

Bryan Whipple Bryan R. R. Whipple, Attorney at Law

If you are licensed, and thus have a right to be paid, you presumably know at least something about the mechanic's lien procedures, which seem to be your best recourse for getting paid or at least getting a trial to determine your rights and enforce them.

Read more
Answered on 10/05/11, 8:39 am


Related Questions & Answers

More Construction Law questions and answers in California