Legal Question in Construction Law in California
i am a subcontractor in california and the general contractor is 6 mos over schdule, cost have goneway up since job started. what rights do i have
Asked on 1/16/11, 10:57 am
1 Answer from Attorneys
Maria Victoria Grabhorn
Law Office of Maria Victoria Grabhorn
Your rights are determined by the kind of contract you have with the GC. You also have your lien rights. Be aware that there has been some recent changes in the lien rights for contractors. While the job is still on going, I would suggest that you consult an attorney.
Answered on 1/25/11, 8:45 pm