Legal Question in Construction Law in California
Unfinished Job
I hired a contractor to do painting. On the first two days we were having
issues (he was leaving early and there were some questions about
workmanship). On the third day he left without notice (he packed up and took
all his equipment) and spent no time working in the house even though work
was supposed to be finished on this day. When we called he said he was
having equipment issues. When we called the store he was supposed to be at
having the ''equipment fixed'' they said he had not been there.
What are we liable to pay this man if anything? I have canceled payment on
the deposit, but want to make sure that I pay him what I am legally obligated
to. Also, can I recoup for additional expenses he has caused? Other
contractors are waiting for the paint to be finished so they can put in flooring
and cabinets, which in turn delays our moving. Plus we had to re-key because
he left with one. Thanks in advance for your responses.
1 Answer from Attorneys
Re: Unfinished Job
First, check to see if he is licensed. If not, you owe him nothing. If he is licensed, it is possible that he materially breached the contract. Only a judge or jury can tell you whether a breach is "material". For the most part, a refusal to adequately man the job after several demands to do so is enough to rise to the level of material breach.
Your damages are the difference between the contract with the abandoning contractor and the cost of finishing the painting with another contractor. You can also likely hold him responsible for consequential damages.
You are entitled to withhold 150% of the amount in dispute. It can sometimes be difficult to determine the amount in dispute. In your case, this could be determined by the bid of the replacement contractor. For example, the bad contractor bid $10,000 to do the job, but the replacement contractor bids $9,000 to finish the work. The bad contractor claims that he's done $2000 worth of work. But, since it's going to cost you at least $1000 more to finish the job ($9000 plus $2000), then $1000 is in dispute so you're entitled to withhold $1500. Re-keying would be consequential damage, so could legitimately be added to the amount in dispute. Basically, consequential damages are any damages that would logically flow from the breach.