can a pool contractor require payment prior to completion of juob


Asked on 4/21/16, 8:23 am

1 Answer from Attorneys

It is legal to request progress payments for work in place and materials delivered to the job site. It is entirely illegal to request payment in full, or for more than the value of work installed and materials delivered at the time of a partial payment.