Legal Question in Civil Litigation in Colorado

Colorado Law - Lien Removal/Satisfaction

Under Colorado law, how much time does a Plaintiff have to remove a lien, once it has been paid in full?


Asked on 1/29/07, 6:42 pm

1 Answer from Attorneys

Philip Rosmarin Rosmarin Law Firm

Re: Colorado Law - Lien Removal/Satisfaction

Depends on what kind of lien. For example, if paid and satisfied, the time limit to remove a mechanics' lien generally is 10 days; a harvesters' lien 30 days; a real property lien 90 days.

Please don't ask this lawyer about ditches' liens.

Read more
Answered on 1/30/07, 12:28 am