Legal Question in Construction Law in Florida

do i need a lien release for each notice to owner against a job or does the final lien release all subsequent notices


Asked on 7/19/10, 7:53 am

1 Answer from Attorneys

For the owner to make proper payments under 713.06, the safest approach is to get a release for each party giving a NTO with each payment application and then final releases prior to final payment

Read more
Answered on 7/19/10, 11:19 am