Legal Question in Construction Law in Florida

Mechanics Lien

We are a subcontractor, I have a

two part question...

1. Can I lien for the full contract price, or just the work that is completed to date?

2. Do I need to file a notice of intent to lien before filing the lien itself?

I would appreciate any help. Thank you!


Asked on 9/18/07, 12:34 pm

1 Answer from Attorneys

Randall Gilbert Gilbert & Caddy P.A.

Re: Mechanics Lien

(1) You can only file a lien for the labor services or material that have been actually furnished to the project. Anything more than that (Even if you have been kicked off) may be considered a fraudulent lien for which there are penalties.

(2) There is no such thing in Florida as a "Notice of Intent To Lien"

However, if you are a subcontractor (i.e. one that is not in direct privity with the owner), then as a precondition to filing a lien you were required to furnish a "notice to owner" within 45 days from commencing.

Good luck, and if you need forms you can always use ours on our website at http://www.theconstructionlawyers.com/

Randall Gilbert

Randall Gilbert

Read more
Answered on 9/18/07, 1:44 pm


Related Questions & Answers

More Construction Law questions and answers in Florida