Legal Question in Construction Law in Georgia

how many days are allowed

If a contractor request a change order for work and it has 10 days of extension. How many days would be added to the contract if the C O is not approved for 30 days but the contractor starts the work.


Asked on 10/04/07, 3:45 pm

2 Answers from Attorneys

Scott Riddle Law Office of Scott B. Riddle, LLC

Re: how many days are allowed

Your relationship with your contractor is based on your contract. We have no way of knowing what your paperwork says about change orders, or any other matter.

Read more
Answered on 10/04/07, 3:48 pm
Glenn M. Lyon, Esq. MacGREGOR LYON, LLC, Business Attorneys

Re: how many days are allowed

Have a local business attorney review the entire contract and he/she will be able to provide a comprehensive answer.

If you would like to discuss any issues further, please feel free to contact my office. My contact information is below. Thank you.

The foregoing is general information only, not specific legal advice. No attorney/client relation has been created or should be implied.

Read more
Answered on 10/04/07, 3:54 pm