Legal Question in Construction Law in Indiana
contractor subcontractor contracts
are ''paid when paid'' clauses legal or inforceable?
Asked on 2/27/07, 3:56 pm
1 Answer from Attorneys
Mark Voigtmann
Baker & Daniels
Re: contractor subcontractor contracts
The answer is yes. However, it may be possible to record a mechanic's lien against the real estate despite the existence of such a clause. Please contact me at [email protected] if you need further assistance.
Answered on 2/28/07, 9:25 am