I am having my house built in Maine and my contractor has breeched the contract. First floor finished was based on a six month timeline that expired on June 30, 2009. The house is not weather tight yet and we're still waiting on three windows. He withdrew 85% of our construction loan and doesn't return calls, emails, text messages. The bank is on him weekly and though we have seen minimal progress ( sheetrock and insulation delivered) it doesn't seem to cut the mustard anymore.
What are my options at this point?
1 Answer from Attorneys
First you need to look at the contract to see what it provides for in case of a breach. Generally with contracts there are a few options at this point, but you will need to take some action soon to preserve your rights and mitigate your damages. Without more information, I can't be more specific. You should meet with an attorney about this, as I assume there is considerable money at stake.
Feel free to call my office to discuss this in more detail.
Related Questions & Answers
-
How does one go about erecting a monument/huge wind turbine on private property?... Asked 9/20/09, 12:50 pm in United States Maine Construction Law
-
Construction problem The slab that my six year old log home sets on has settled more... Asked 11/01/08, 10:25 pm in United States Maine Construction Law