My contractor is 120 days overdue. Do I have the right to deduct a fee per day? How would I determine what an appropiate fee would be?


Asked on 4/03/08, 4:26 pm

1 Answer from Attorneys

John Corbett Corbett Law Firm LLC

Re: Construction Contract

A lot depends on the details. If a contractor is unreasonably late with construction, you may be able to throw him off the job and get someone else to finish. That has to be done carefully though because you don't want a judge to think that you are the party breaching the agreement. Best to speak with your lawyer.

My firm handles matters of this type. If I can be of further help to you, call or email.