Legal Question in Business Law in New York

Began job with only an estimate(build garage) ,

Home owner agreed, signed estimate.

Then changed entire project several times, ie; stlye of roof, added icf to normal concrete plan,

.. greatly affecting build time. Can we charge for this extra labor time, on our invoice?


Asked on 1/21/22, 7:15 am

1 Answer from Attorneys

David Slater David P. Slater, Esq.

Yes. Submit a new agreement as job has changed. I would do no further work until signed.

Read more
Answered on 1/21/22, 7:32 am