Began job with only an estimate(build garage) ,
Home owner agreed, signed estimate.
Then changed entire project several times, ie; stlye of roof, added icf to normal concrete plan,
.. greatly affecting build time. Can we charge for this extra labor time, on our invoice?
Asked on 1/21/22, 7:15 am
1 Answer from Attorneys
David Slater
David P. Slater, Esq.
Yes. Submit a new agreement as job has changed. I would do no further work until signed.
Answered on 1/21/22, 7:32 am