Legal Question in Construction Law in New York

Contesting a lien

I'm in my early twenties and a first home owner. I had my kitchen and bathroom revitalized. Them contractors I hired

did a terrible job, left celings and walls cracked without finshing it with a coat of spackle and plaster. They also did not hook up the drain pipes for the vanity and kitchen faucet. Also, while they were demolishing my bathroom wall they even broke a few pieces of my bedroom wall down and left it unpatched. I gave them 30 days to complete the entire project and they had exceeded by an extra two weeks. Since I live in a coop, mandatory rules are applied as a result each calendar day that the contractors do not finish, a fee of $30 is applied. I stopped payment on the final payment and the contractor left and said he would put a lien on my apartment. Bottom line I want another

company to finish. How do i

contest this?, will I be receiving a notice or letter of some sort from the contractor indicating I've been leined?, How do I serve a notice to particularize the lein?, Should I counter suit ? The quality of work

was so poor and took so many extra

days. I had to

take off from work for a month and a half to be home.

Any

advise would be helpful.


Asked on 11/18/08, 11:33 pm

2 Answers from Attorneys

Michael Markowitz Michael A. Markowitz, PC

Re: Contesting a lien

A lien on a cooperative is a little different than a lien on a homeowner. A mechanic's lien for improvements to cooperative apartment is enforceable against cooperative building owner only where latter has affirmatively consented to work authorized by tenant-shareholder. Newman v. Valmar Elec. Co., 2005, 9 Misc.3d 450, 801 N.Y.S.2d 731. If the cooperative did not affirmatively consent to work performed by the terrible contractor, the lien would be a nullity.

However, if the contractor did file a lien against the coop, he would have to serve notice of lien on both you and the cooperative. Normally, under a proprietary lease agreement you would have the duty to discharge the lien by filing a bond. It is not as difficult as you would think.

You are correct that you may demand information to particularize the lien. Failure to particularize the lien upon proper demand gives grounds to file a motion to vacate the lien.

What I would do is send a certified letter to the contractor firing the contractor. The letter should set forth the reasons why the contractor is being released.

I would then immediately retain another contractor to repair the damage and complete the job. The difference in price are you damages which are actionable against the contractor. You would then have the decision of suing the contractor for damages or, if the contractor commenced an action against you, counterclaiming the contractor for damages.

Mike.

Read more
Answered on 11/19/08, 8:08 am
Marshall Isaacs Marshall R. Isaacs, Attorney At Law

Re: Contesting a lien

I sympathize with your situation. The construction industry has its fair share of incompetent and fiscally-irresponsible contractors. I deal with them on a daily basis.

There is no simple "answer" to your inquiry. You have a number of remedies available which a skilled construction litigator can walk you through.

The one thing I can tell you is that there is nothing you can do to prevent the contractor from filing/serving a Mechanic's Lien. The mechanic's lien itself is generally somewhat harmless as it is difficult and expensive for a contractor to foreclose on a mechanic's lien.

The problem for you, however, is that the mechanic's lien is filed against the entire building, not just your apartment. Once the lien is filed, you will be required by your co-op board to resolve/remove the lien or they will almost definitely litigate against you.

I highly recommend that you promptly speak to an attorney to address the problem before your proprietary lease is at risk.

Read more
Answered on 11/19/08, 8:05 am


Related Questions & Answers

More Construction Law questions and answers in New York