Legal Question in Construction Law in New York

Liens

A subcontractor placed a lien for materials furnished on a public improvement job on a prime contractor. The lien was for the amount of the materials and did not include interest. Is the prime contractor liable for interest? If so, may the subcontractor refuse to discharge the lien after the prime contractor has paid the amount in full and the sub has cashed the check? Thanks for your help!


Asked on 11/10/03, 4:00 pm

1 Answer from Attorneys

Michael Markowitz Michael A. Markowitz, PC

Re: Liens

If the lien was paid in full the subcontractor (materialman) must discharge the lien.

Mike.

Read more
Answered on 11/11/03, 9:47 am