A contractor did a deficient and incomplete job on our home as verified by a licensed architect/expert. The contractor has ignored my attempts to communicate with him and has now filed a mechanic's lien for the full amount he claims is due. What recourse do we have to get this lien removed?


Asked on 6/12/09, 6:21 am

1 Answer from Attorneys

Michael Markowitz Michael A. Markowitz, PC

Re: Mechanic's Lien

You may demand an itemized statement under NY Lien Law section 38. If the contractor fails to provide the statement, you may petition the Court to vacate the lien.

Mike.

Read more
Answered on 6/12/09, 9:31 am