Legal Question in Construction Law in North Carolina
Why in north Carolina dose a construction lien not require a lien amount when filed with the clerk of court.? How would you get an amount.
.
Asked on 2/23/11, 6:48 pm
1 Answer from Attorneys
Jeff Rosner
Rosner Law Firm P.A.
According to the statute, the amount is required. the statute says that a claim of lien should contain the following including
(6) General description of the labor performed or materials furnished and the amount claimed therefor:
Answered on 2/24/11, 5:42 am