Legal Question in Construction Law in Ohio

Contruction Lien in Ohio

We installed work as a subcontractor back in Jan '08. We have not been paid in full. Is it too late to file a lien against the property?


Asked on 4/29/08, 1:41 pm

1 Answer from Attorneys

J. Norman Stark J. Norman Stark , Attorney, Architect

Re: Contruction Lien in Ohio

Dear Subcontractor: You have 75 days from the last day of work on the job, within which to file your lien, or you are time barred (too late). Here's a part of an article available without charge or obligation, on my Website,

MECHANIC�S LIENS �TOP TEN ERRORS

Under the provisions of Ohio�s Mechanic�s Lien laws, an affidavit to obtain a mechanic's lien must be filed within 75 days after the contractor or materialman (materialperson) last furnished or provided services or materials. Other important changes now require the filing (recording) of Notice of Commencement ("NOC") by the Owner, and a Notice of Furnishing ("NOF") by each contractor, subcontractor or materialman (materialperson) first performs work or supplied materials. Service of this Notice of Furnishing is a mandatory prerequisite to obtaining a valid mechanic�s lien!

The following is a list of the ten (10) most frequent errors noted which may result in contested or invalid liens:

1. Notice of Furnishing (�NOF�) must be served, by Certified Mail within 21 days after beginning work or providing materials. See statutory form, Sect. 1311.05(B). NOF served late relates back only for work and materials provided within 21 days prior to service of NOF. Serve NOF upon owner where contract is with original contractor. Serve NOF upon Owner and original contractor where contract was with a subcontractor. Where NOF not recorded, NOF not required until NOTICE OF COMMENCEMENT ("NOC") is recorded.

2. Failure to serve NOF on Owner, General Contractor and Subcontractor within 21 days of claimant's first work or delivery of materials.

3. Failure to Serve NOF Properly, i.e. by Certified Mail or other means, with signed receipts to support proof of timely, proper service by: (a)Sheriff, or Special Deputy, with formal return required, (b) Certified Mail, Return Receipt Requested, (c)Registered Mail, Return Receipt Requested, (d) Overnight Mail, with U.S. Postal Service Receipt, (e) Messenger, with receipt, (f) FAX, with receipt, (g) FED-X, UPS, etc., with receipt.Consulrt an experienced construction counsel for advice, guidance and assistance.

Pursue collection of the money owed you for your work, materials and services with the same enthsuiasm as when you did the work!!

Good luck.

Sincerely,

J. Norman Stark

Read more
Answered on 4/29/08, 4:07 pm


Related Questions & Answers

More Construction Law questions and answers in Ohio