What are the significant dates for a commercial mechanics lien filig


Asked on 10/31/09, 8:53 pm

1 Answer from Attorneys

J. Norman Stark J. Norman Stark , Attorney, Architect

Dear Inquirer: An affidavit to obtain a mechanic's lien (on other than 1 or 2 family dwelling or condo unit) must be filed within 75 days after the contractor or materialman (materialperson) last furnished or provided services or materials. On 1 or 2 family dwelling or condo unit, lien must be filed within 60 days after the contractor or materialman (materialperson) last furnished or provided services or materials. The revised mechanic's lien laws now also require the filing (recording) of Notice of Commencement ("NOC") by the Owner, and a Notice of Furnishing ("NOF") by each contractor, subcontractor or materialman (materialperson) who first performs work or supplied materials. Service of this Notice of Furnishing is a mandatory prerequisite to the ability to obtain a valid lien.

'hope this answers your quuestion. Sincerely, J. Normsan Stark

Read more
Answered on 11/06/09, 9:43 am


Related Questions & Answers

More Construction Law questions and answers in Ohio