Legal Question in Construction Law in Texas

mechanics lein

what are the procedures for filling a mechanics lein


Asked on 2/22/06, 1:15 pm

1 Answer from Attorneys

Peter Bradie Bradie, Bradie & Bradie

Re: mechanics lein

Basically you have to give notice of non-payment and then file your lien affidavit with a copy to the owner and the general contractor. The notices are always sent by certified mail.

The timetables depend upon whether you're the general conytractor, a sub to the general, or a sub to a sub.

Details are spelled out in Section 53 of the Texas Property Code.

Read more
Answered on 2/22/06, 1:28 pm


Related Questions & Answers