Which form would be appropriate for a sub-contractors lien against a contractor or property for non payment of labor?

thanks

Vickie


Asked on 1/24/02, 2:54 pm

1 Answer from Attorneys

Peter Bradie Bradie, Bradie & Bradie

Re: Subcontractor Liens

First you need to send timely notice of non-payment to the owner of the real property by certified mail, with a copy to the prime contractor. Then you need to timely prepare and file a Mechanics & Materialman's Lien Affidavit in the real property records in the county where the property is located. The owner and the prime contractor also receive a copy of the affidavit by certified mail.

I'm not familiar with all the forms available here. We use our own forms for our clients.

Read more
Answered on 1/24/02, 3:39 pm