What does the following statement mean??? ''Time is of the essence in Supplier's performance under this Agreement''.


Asked on 2/07/01, 10:43 am

1 Answer from Attorneys

Daniel Press Chung & Press, P.C.

Re: Supplier Responsibility

It means that failure to perform by the date fixed in the contract for performance is a material breach of the contract. Otherwise, reasonable delays are not considered material breaches.