Legal Question in Construction Law in Virginia
mechanic's lien on an addition
We had a two room addition completed, based on a written contract. Additional items were completed during the job and the contractor attempted to bill us afterwards. Can he claim this on a mechanics lien? We are refusing to pay, since no written change order was completed.
Asked on 3/20/09, 5:33 pm
1 Answer from Attorneys
Michael Hendrickson
Law Office Michael E. Hendrickson
Re: mechanic's lien on an addition
More facts are needed to reliably answer this inquiry, but if these additional items that were completed by the contractor without a written change order were reasoanbly connected with the completion of the two room addition, their costs may be enforceable under the original written agreement and validly subject to a mechanic's lien.
Answered on 3/21/09, 1:56 pm