Legal Question in Construction Law in Virginia

mechanic's lien

Contractor terminated for cause - as per terms of contract - about 66% through project. Four months later he files a mechanic's lien, for balance of project $[$90000]. This is for work not performed or materials not provided. Also, his claim is that one sub he used was hired by our new contractor. Now he is filing to enforce claim, Does Virginia have a basic hearing procedure to dismiss this claim or must there be a formal suit filed?


Asked on 9/24/08, 5:22 pm

1 Answer from Attorneys

Daniel Press Chung & Press, P.C.

Re: mechanic's lien

There is a process to summarily remove mechanics liens. Let me know if you need assistance with this.

Read more
Answered on 9/24/08, 11:22 pm