Contract6ors Lien Rights
I was wondering if you can tell me if a contractor who never filed a 20 pre-lien and who also walked away and did not finish the job, are they entitled to file a lien against my property for o/s invoices he claims we owe him?
Asked on 2/25/09, 11:03 am
2 Answers from Attorneys
Bryan Whipple
Bryan R. R. Whipple, Attorney at Law
Re: Contract6ors Lien Rights
The requirement to file a 20-day preliminary notice does not apply to a prime contractor who is in direct contract with the owner.
Answered on 2/25/09, 11:53 am
Terry A. Nelson
Nelson & Lawless
Re: Contract6ors Lien Rights
Entitled or not, if he does you have to respond.