Legal Question in Construction Law in Colorado

is there a cost to file a mechanics lien in Colorado?


Asked on 2/16/11, 8:22 am

1 Answer from Attorneys

Eric Fisher Law Office of Eric A. Fisher. LLC

I believe the filing fee is set by the County Clerk and Recorder.

In Summit County it is $5 per page.

The law regarding mechanics liens is complex and must be followed to the letter to be able to foreclose on the lien. For example, notice must be provided at least 10 days before filing.

If you are seeking legal advise on such matters and you are in Summit County, please contact us.

The Law Office of Eric A. Fisher, LLC

970-668-1949

Read more
Answered on 2/16/11, 12:20 pm