Breech Of Contract
We signed a contract with a general contractor almost
2 years ago, the job was to begin september 8,2003
and to be completed january 8,2004.
We were just informed to start this job in november 2004
my question is Did The General Contractor cause a
breech of contract,by not starting the job when they
were suppose to.
1 Answer from Attorneys
Re: Breech Of Contract
It would probably be a breach of contract if they delayed beginning the project over a year late, but it depends on the circumstances. For example, the delay may be excused by unusual weather.
If you would like to discuss any issues further, please feel free to contact my office. My contact information is below. Thank you.
The foregoing is general information only, not specific legal advice. No attorney/client relation has been created or should be implied.
Glenn M. Lyon, Esq
MacGregor Lyon, LLC
Promenade II
1230 Peachtree Street NE
Suite 1900
Atlanta Georgia 30309
Phone 404.942.3545
Fax 404.795.0993
www.macgregorlyon.com
Confidentiality Notice
This message is being sent by or on behalf of a lawyer. It is intended exclusively for the individual or entity to which it is addressed. This communication may contain information that is proprietary, privileged or confidential or otherwise legally exempt from disclosure. If you are not the named addressee, you are not authorized to read, print, retain, copy or disseminate this message or any part of it. If you have received this message in error, please notify the sender immediately by e-mail and delete all copies of the message.