Legal Question in Construction Law in Illinois

construction

We had hired a contractor and he gave us his bid for work. half way through this project he went over cost again and gave us a new price sheet for $30 thousand more. Can he do this? We hired him because of his bid, and now he tells us we owe him more money. Plus he added more money onto labor. Is this right!!


Asked on 10/04/07, 11:59 am

1 Answer from Attorneys

Patrick Tracy Patrick J. Tracy, Esq, P.E.,

Re: construction

The real question is whether there was a contract to perform. Was there a written agreement? Did you sign a proposal to create an agreement?

Without further information I cannot comment.

Read more
Answered on 10/04/07, 12:11 pm